Construction site H41 Sill-Pfons Gorge: TBM Lilia has also completed her first 4 km

TBM Lilia is close to her halfway point: on Sept. 22nd 2024, she completed the first 4 kilometres along the east line...

"Wilma" and "Olga", the last TBMs of the Brenner Base Tunnel, have been launched

Today’s ceremony marked the start-up of the last two tunnel boring machines to work on the Brenner Base Tunnel. Working...

First breakthrough of a main tunnel in Austria

Another successful milestone for the Brenner Base Tunnel - breakthrough of the east tunnel - connection of the two...

Emergency management in the BBT project: foundations laid for cross-border cooperation

Emergency response activities in case of rail traffic breakdown play a key role in construction of the Brenner Base...

Construction site H41 Sill Gorge-Pfons: TBM Ida reaches its halfway point

TBM Ida has reached her halfway point: on 22nd July 2024, she completed the excavation of the first 4 kilometres along...

Tubbing ring production in the BBT project: a model of environmental sustainability

Tubbing rings are precast concrete elements that form the final lining of the tunnels. Environmentally sustainable...